As a previous mine pit and tailings pond, the Base Mine Lake has residual bitumen forming two mats on the lake floor. Keller designed and installed a shoring solution to create a new dock area for dredging operations for bitumen removal.
The mine owner, Syncrude, planned to remove the bitumen using mechanical dredging technology. However, an unloading dock had to be built to unload dredging barges. A shoring solution was required to retain the soils from sloughing into the dredge area and increase the stability of the shoreline for dock construction. Heightened safety awareness was required to work on and near water and tight working areas.
Learn more about Keller's North America Shoring Solutions
The general contractor placed berms around the 50 ft by 75 ft (15m by 23m) dock area to protect equipment and crews from being able to contact the water. Test pits were dug to assess the potential of construction-related soil liquefaction. Once the site was appropriately evaluated, Keller designed and installed a cantilevered sheet pile earth retention system, using sheet piles installed to 40 ft (12m) deep from shore level. In several instances predrilling was required to allow for sheet pile penetration through hard soil layers. A continuous cap plate was installed along the top of the sheet piles enabling the boats to tie off onto the wall.
Learn more about Keller's North America Sheet Pile Expertise
Source: Syncrude Base Mine Lake
The Regional Municipality of Wood Buffalo has a long history of overland flooding since 1835, with...
Keller, world’s leader in geotechnical solutions, announces the completion of its first interlockin...
With its unique, award-winning, design resembling a cantilevered stack of books, the Center for Com...
Keller North America provided slope stabilization and deep foundations solutions for culvert constr...
Keller installs auger cast piles for the first FDOT project in over half a century, supporting a ne...
It’s a complex project. The new buildings will be right in the heart of the campus, linked to exist...
Keller will participate in a Miami project in which, for the first time in 50 years, auger cast pil...
Keller’s ground improvement work wins the 2022 CalGeo Outstanding Project award. In 1916, marshla...
When subjected to wet and dry cycles, the claystone bedrock exhibited expansion and contraction, be...