Keller Poland has completed its first marine combi-wall project in Gdansk Port, Poland, helping with the expansion of one of Europe's busiest ports. Gdansk port on the southern side of the Baltic Sea is a major transportation hub, linking the Nordic countries with vital trading routes into Southern and Eastern Europe. Following a €140 million investment from the European Union, the port is in the midst of a vast program of works that will improve road and rail links and upgrade the inner port's network of busy quays.
Keller was awarded the project by general contractor Budimex, the country's biggest construction company. Keller Poland has successfully completed a new 1.2km retaining wall, allowing the fairway to be deepened from 3m to 12.5m and enabling larger cargo vessels to use the route at Dworzec Drzewny quay.
"We have completed many successful infrastructure projects for Budimex over the years," says Keller Technical Director Rafał Buca. "About three years ago the company became active in the marine sector and we took advantage of that opportunity to also expand into this market. They trusted us to design this complex project and execute it flawlessly, and that's what we did."
The project wasn't without its challenges. "In our initial design analysis we knew that traditional sheet piles would not be sufficient for the loads required, so we proposed a combi-wall, which consists of steel tubes and sheet piles. The use of a combi-wall together with raked large diameter continuous flight auger [CFA] piles under the slab form a strong quay wall foundation."
The project began in December 2018 with the CFA piles. In total, the team installed 47,145m of piles (2,245 with an average length of 21m), 437 steel piles of up to 26m long (just under half of which were installed in the water) and 477 double sheet piles of up to 17m long. Works also included a 233m temporary sheet pile wall constructed offshore to protect the 160t crane.
"The wind and the waves, particularly towards the end of winter, were the biggest challenge, so we had to ensure a safe working environment for our crew," adds Site Manager Tomasz Rybarczyk. "The team also carried out a number of rigorous tests. This included 17 static load tests, seven tension load tests and over 560 pile integrity tests."
The project wrapped up at the end of October 2019 and Rafał believes its success will pave the way for more work in the marine sector.
Source: Keller
Keller, world’s leader in geotechnical solutions, announces the completion of its first interlockin...
Keller will participate in a Miami project in which, for the first time in 50 years, auger cast pil...
Keller recently brought its engineering expertise and experience of working on open water to a chal...
Keller North America provided slope stabilization and deep foundations solutions for culvert constr...
The growth in demand for aged care facilities in Australia has led to an increase in private develop...
It’s a complex project. The new buildings will be right in the heart of the campus, linked to exist...
With its unique, award-winning, design resembling a cantilevered stack of books, the Center for Com...
Keller installs auger cast piles for the first FDOT project in over half a century, supporting a ne...
The Regional Municipality of Wood Buffalo has a long history of overland flooding since 1835, with...